Joint action plan targets recurring Bajghera underpass waterlogging
Joint Action Plan Targets Recurring Bajghera Underpass Waterlogging
Bharatmorningnews.com – Civic agencies have finalised a comprehensive joint action plan to permanently address the persistent waterlogging issue at the Bajghera underpass on the Dwarka Expressway. According to the Gurugram Metropolitan Development Authority (GMDA), which announced the decision on Wednesday, the strategy involves constructing table-top barriers on approach roads and installing surface drains along Bajghera Road. This joint action plan targets recurring flooding that has plagued commuters for years, particularly during monsoon seasons.
The strategic decision emerged from a coordination meeting held between officials of GMDA, National Highways Authority of India (NHAI), and Public Works Department (PWD). The meeting was convened after heavy rainfall on Tuesday evening caused severe waterlogging at the underpass, forcing authorities to close the critical traffic route to vehicles. The incident highlighted the urgent need for coordinated infrastructure improvements to prevent future disruptions.
Agency Responsibilities and Implementation Timeline
A GMDA spokesperson explained that responsibilities have been clearly divided among the three participating agencies to ensure faster execution of the proposed works. The timeline is designed to complete essential improvements before the next spell of heavy rainfall arrives. GMDA CEO PC Meena outlined the specific roles assigned to each organization in the comprehensive drainage improvement project.
NHAI will construct table tops on the approach roads to regulate the flow of stormwater towards the underpass during heavy rain. The authority will also inspect the existing sump wells and pumping infrastructure and undertake repairs or upgrades wherever required to improve drainage efficiency.
Meena further clarified that the Public Works Department’s Building and Roads division has been tasked with constructing surface drains along Bajghera Road. These new drains will connect to GMDA’s Leg-1 master drain system, allowing quicker discharge of stormwater into the city’s primary drainage network. This connection is expected to significantly reduce the chances of water accumulation at the Bajghera site during intense rainfall events.
Immediate Measures and Infrastructure Upgrades
GMDA officials confirmed that a joint inspection of the underpass was conducted on Wednesday to assess current conditions and plan immediate interventions. Vikram Singh, executive engineer at GMDA, reported that a super sucker machine has been deployed to clear silt from the Leg one drain. The cleaning operation will cover approximately 300 metres of the drain stretch to ensure that no water spills out from the drain during heavy rainfall.
The comprehensive approach includes both immediate cleanup efforts and long-term infrastructure modifications. Table-top barriers will help control water flow direction, while the new surface drains will provide additional capacity for stormwater management. The coordination between multiple agencies represents a significant step toward sustainable urban drainage solutions in Gurugram.
FAQ: Understanding the Bajghera Waterlogging Solution
Q: When was the joint action plan for Bajghera underpass finalised? A: The plan was finalised and announced by GMDA on Wednesday following a coordination meeting with NHAI and PWD officials.
Q: Which agencies are involved in implementing the waterlogging solution? A: Three main agencies are participating: Gurugram Metropolitan Development Authority (GMDA), National Highways Authority of India (NHAI), and Public Works Department (PWD).
Q: What specific infrastructure improvements are being made? A: The improvements include table-top barriers on approach roads, surface drains along Bajghera Road, inspection and repair of sump wells and pumping infrastructure, and silt clearance from the Leg-1 master drain.
Q: How much of the drain will be cleared immediately? A: Approximately 300 metres of the Leg one drain will be cleared using a super sucker machine to prevent water spillage during heavy rainfall.
Q: What is the expected benefit of connecting drains to Leg-1 master drain? A: The connection will allow quicker discharge of stormwater into Gurugram’s primary drainage network, significantly reducing water accumulation at the Bajghera underpass location.
Q: When will these improvements be completed? A: The work is scheduled to be completed before the next spell of heavy rainfall, ensuring the underpass remains functional during peak monsoon conditions.